Toggle menu

Find out about Ash Road Bridge

What you need to know about Ash Road Bridge

a 3D computer generated image showing ash road bridge going over the railway

The Ash Road Bridge scheme is an important infrastructure project. It is part of the Council's Local Plan (Policy A31).

It will enable housing that has been allocated in the Local Plan to come forward and will close Ash level crossing.

The closure will improve safety for local residents and users of Ash train station. It will also reduce traffic congestion in the area.

The scheme will encourage traffic off rural roads. Traffic currently uses rural roads to avoid the level crossing. This will remove the safety hazard posed by the present level crossing. 

The level crossing closes around eight times an hour or 150 times a day. This currently amounts to closure periods of up to 25 minutes per hour.

The level crossing will be closed to vehicle traffic when the road bridge opens. 

Pedestrians and cyclists will still be able to cross the railway at the level crossing until such time as a footbridge is installed.

Key dates

  • preparation works July to August 2023
  • main construction starts September 2023
  • new bridge installation December 2023 to October 2024
  • Foreman Road closures November 2023 to July 2024
  • new link road and bridge open to traffic October 2024
  • completion February 2025

Project updates for Ash Road Bridge

May 2024

  • 19 bridge beams are being installed over the railway over the early May Bank Holiday, 4 to 6 May: A viewing area will be open on the south site at Foreman Road on Saturday 4 May and Sunday 5 May. Book to visit at 10am or 4pm on both days. Email ashroadbridge@volkerfitzpatrick.co.uk to book your place. Limited parking is available on site
  • rail replacement buses will run between Ash and Guildford over the weekend. Check the National Rail website (opens new window) before travelling

April 2024

  • surfacing of Phase 1 of Foreman Road (Guildford Road to Foreman Park) is due to take place before the end of April following installation of curbs, edging and ducting
  • key work ongoing for the structures on both the north and south sites to be ready for the beam installation in early May
  • phase 2 of Foreman Road (Foreman Park to Vyne Walk) will now start in May. The traffic management will alter with Foreman Road closed from Foreman Park to Vyne Walk. This will only affect people driving to and from Foreman Park
  • our contractor Volker Fitzpatrick Limited, scored 45 out of a possible 45 points at its latest Considerate Constructors Assessment on 11 April

March 2024

  • diversions for British Telecom, water and high voltage cables were completed on Foreman Road
  • drainage was being installed on Foreman Road Phase 1
  • flood relief culvert on the north site was completed
  • pile caps were installed on the north and south
  • scaffolding and shuttering installed on the north abutment (supporting structure for the bridge) and is being progressed to the south abutment
  • Year 10 students from Ash Manor school visited the site on 20 March

February 2024

  • we, as environmental health authority, have given permission for weekend working until the first May Bank Holiday, 6 May 2024. Our contractor has agreed to adhere to stringent noise limits. This is so we can meet important deadlines
  • piling is now complete on both the north and south sites
  • the new Foreman Road roundabout (opposite Vyne Walk) is progressing well
  • kerbs have been installed on the new roundabout and southside embankment
  • the drainage pond has been dug for the northside embankment
  • drainage pipes are being installed at north end of Foreman Road
  • the Foreman Road entrance to site has been surfaced and the wheelwash is working

Piling machine with drill bits laying on the floor

Continuous Flight Auger (CFA) piling complete, south wing walls.

Pilings in the ground all completed

Blinding complete, north west wing wall.

January 2024

  • the piling rig will move back to the south site on Friday 26 January
  • we hope that piling will be completed by the middle of February

December 2023

  • piling work is taking longer than planned on the south side of the site. This is due to poor weather and unexpected ground conditions. We, as environmental health authority, has given permission to extend working hours on site to enable the piling to be completed by the end of January
  • when necessary, work will go on until 8pm Monday to Friday
  • our contractor, Fitzpatrick (VFL), raised £1000 from its supply chain to buy Christmas presents for children whose families receive food parcels from the Ash Villages Food Parcel Project (opens new window)

some members from Volker Fitzpatrick, the Food Parcels Project team and councillor Carla Morson standing next to a Christmas tree and a pile of donated christmas presents

Pictured above are members of the Food Parcels Project team, some of the VFL team and Cllr Carla Morson.

October 2023

South side of railway

  • site set-up for the main offices including parking for project staff
  • construction and testing of the south piling mat before piling starts in November
  • main embankment constructed and continues to settle. This can take several weeks

View from above of the south side of the building site. A mound of earth has been constructed that will form part of the bridge.

North side of the railway

  • satellite welfare facilities for staff installed
  • construction and testing of the north piling mat
  • main embankment construction to roof of the new flood relief culvert
  • Orchard Farm land raising almost complete
  • excavation and topsoiling of flood attenuation areas

View from above of the north side of the building site. Heavy Machinery are moving mounds of earth.

September 2023

We held two drop-in sessions in September for residents in Ash who wanted to find out more about the project.

July 2023

  • Volker Fitzpatrick has been appointed as the main contractor for the project
  • site preparation and pre-construction began on Monday 24 July
  • construction work starts in September 2023
  • the work is expected to take approximately 18 months

Traffic management updates for Ash Road Bridge

While work on the bridge is taking place the following will be in place:

  • local diversions will be signposted at these times
  • traffic calming measures will be used on residential roads
  • residents will be notified in advance

Phases of the diversion routes

Foreman Road will be closed in sections to through traffic in between November 2023 and January 2025. Note that dates may change due to unforeseen circumstances.

Phase 1

Ash Church Road to Foreman Road junction
27 November 2023 to mid-May 2024

Phase 2

Foreman Park to Vyne Walk
Mid-May 2024 to 17 June 2024

Phase 3

Vyne Walk to Foreman Road Site Exit
17 June 2024 to 12 July 2024

Phase 4

Grange Road
12 July 2024 to 25 July 2024

Phase 5

Ash Church Road and Guildford Road
15 October 2024 to 8 January 2025

Road closure interactive map

Use the interactive map to view all five stages of diversion routes planned. Tick one phase at a time only. 

Footpath closure interactive map

Use the interactive map to view footpath diversion routes planned for phase one.

Detailed maps

View Ash Road Bridge detailed maps:

Contact us about Ash Road Bridge

You can contact us to:

  • ask questions
  • provide feedback or
  • subscribe to regular updates and a quarterly newsletter

by emailing ashroadbridge@volkerfitzpatrick.co.uk